Wind farm idea zapped back to life

Email

MADISON - The clock began ticking Friday on state regulators to review an application to construct a 102.5 mega-watt wind energy farm in the towns of Forest and Cylon.

By statute, the Wisconsin Public Service Commission has 30 days to determine if the application submitted by Highland Wind Farm LCC is complete, and if so, then six months to approve or deny it. If necessary, a circuit court can grant the PSC a six-month extension.