I-94 bridge work to affect St. Croix traffic with overnight lane closings

Work to replace the 200th Street Bridge over I-94 in St. Croix County will result in overnight lane closures from Monday to Friday, May 2-6.

The closures will take place between Roberts and Baldwin (Exit 10 (Hwy. 65) and Exit 19 (Hwy.12).

The closures are required to remove the existing 200th Street Bridge.

Westbound I-94 is scheduled to be closed to traffic during the following times:

--10:30 p.m. Monday, May 2, to 5 a.m. Tuesday, May 3

--10:30 p.m. Tuesday, May 3, to 5 a.m. Wednesday, May 4

During these times, westbound traffic will be detoured onto Hwy. 12 from Exit 19 to Exit 10 (Hwy. 65).

Eastbound I-94 is scheduled to be closed to traffic during the following times:

--10:30 p.m. Wednesday, May 4, to 5 a.m. Thursday, May 5

--10:30 p.m. Thursday, May 5, to 5a.m. Friday, May 6

During these times, eastbound traffic will be detoured onto Hwy. 12 (Exit 19) from Exit 10 (Hwy. 65).

Additional single-lane closures are expected each day from 5-8 a.m. and from 6-10:30 pm.

A new bridge is expected to be completed and opened to traffic later this summer.